The Dakota Access oil pipeline's opening is in limbo now that the U.S. Army has denied critical permits for a water crossing near the Standing Rock Sioux reservation.
For the pipeline's developer, Dallas-based Energy Transfer Partners, that's particularly bad news. Delays already have cost it nearly a half-billion dollars. Losses are tallying daily, and oil shippers could soon demand to renegotiate contracts.
But for North Dakota's overall oil industry, the pipeline's delay isn't a big short-term issue since petroleum production is in the dumps. That's not likely to change much in 2017, as the global oil glut is expected to linger.
"As production has declined, [Dakota Access] is a little less critical," said Lynn Helms, head of North Dakota's Department of Mineral Resources.
By mid-2018, however, the state is forecasting higher production. "Out beyond that, [Dakota Access] becomes very significant," Helms said.
The 1,172-mile pipeline through four states is 92 percent complete. But last Sunday, the U.S. Army's Civil Works Department denied easements for the pipeline to be built 95 feet below the bottom of Lake Oahe.
The U.S. Army Corps of Engineers had signed off on the lake crossing last summer when it approved an environmental assessment for the Dakota Access pipeline. But protests have grown since then, led by the Standing Rock tribe's concern over the pipeline's effect on its water and cultural heritage.
So, the Army Corps delayed bestowing easements, the final regulatory action needed for Dakota Access to cross Lake Oahe. The Army is now calling for a deeper look at alternative routes, and it's recommending a full Environmental Impact Statement, a process that could take a year.