ADVERTISEMENT

Nuke lab system to cost $41 million to fix

  • Article by: JERI CLAUSING
  • Associated Press
  • November 9, 2012 - 5:28 PM

ALBUQUERQUE, N.M. - Officials at Los Alamos National Laboratory say the estimate for fixing the new but inoperable security system at the nation's bomb building lab has doubled.

Lab officials Friday confirmed a report in the Albuquerque Journal that it could cost an additional $41 million and take six months to fix the $213 million system, which has been under construction for seven years and was supposed to be complete this summer.

That is double what officials estimated a few weeks ago, when problems with the security system were first reported.

In a memo to staff this week, lab director Charles McMillan called performance on the project "unacceptable" and said it has damaged the lab's credibility.

© 2014 Star Tribune