Xcel Energy repeatedly mismanaged a major upgrade to its Monticello, Minn., nuclear power plant, and deserves blame for $402 million in cost overruns that more than doubled the final price tag, according to investigative findings released Monday.
The report by an administrative law judge investigating the matter rejected virtually all of the Minneapolis-based utility's explanations for how the project, approved in 2006 and completed in 2013, ended up costing $748 million, an increase of 114 percent in today's dollars.
"We are disappointed with the administrative law judge's recommendation regarding the Monticello nuclear plant's life extension and power uprate project," Chris Clark, president of Xcel's Minnesota regional unit, said in a statement.
The project increased the output of the 1970s-era power plant by nearly 12 percent, although Xcel still hasn't run the reactor at the higher output. The work, done mainly during shutdowns in 2009, 2011 and 2013, also replaced equipment to keep the plant running another 20 years.
Judge Steve Mihalchick, who presided over the state's investigation, concluded that Xcel mishandled the project from the beginning, failing to recognize the complexity of the upgrade and the resulting higher costs.
"Xcel's principal failure was that it did a very poor job managing the initial scoping and early project management up until beginning installation during the 2009 refueling outage," Mihalchick wrote in a 38-page report to the Minnesota Public Utilities Commission.
Despite the findings, ratepayers may not be off the hook for the overruns.
The commission will decide how much of the extra costs Xcel and its investors must bear — and how much should be applied to customers' rates. Mihalchick said he agreed with a state Commerce Department recommendation that would sock Xcel for only a share of the costs —$71 million — with the remainder applied to rates.