Moving on up: Vikings stadium plan adds escalators, TVs

  • Article by: ROCHELLE OLSON , Star Tribune
  • Updated: June 21, 2014 - 9:34 AM

Vikings are kicking in $1.3M to buy six more escalators, 1,180 TVs for new multi-purpose building.

hide

The stadium construction site was bustling Friday under sunny skies. Through the end of May, $89 million has gone into the site, a Mortenson Co. official said.

Photo: ROCHELLE OLSON • raolson@startribune.com,

CameraStar Tribune photo galleries

Cameraview larger

Getting into the new Minnesota Vikings stadium is likely to be even smoother with the addition of six new escalators to its entryway design.

That will bring the total of main-entry escalators at the Minnesota Multipurpose Stadium to 18. All told, the stadium — scheduled to open in 2016 on the site of the now-vanished Metrodome — will have 33 escalators.

Another addition: 1,180 more televisions, bringing the total to 2,000.

Ease of vertical circulation is critical to stadiums, Vikings Vice President Lester Bagley said Friday. Time and again, other teams around the league delivered that message; Bagley noted that Indianapolis said it wished it had installed more escalators in the Colts’ Lucas Oil Stadium.

Minneapolis’ bid for the 2018 Super Bowl, which focused heavily on the new stadium, recently won out over bids from Indianapolis and New Orleans.

“We’re going to have a building that we can move food, people, emergency equipment around in a quick manner,” said Ted Mondale, executive director of the Minnesota Sports Facilities Authority.

The authority approved changes to the stadium budget for design-consulting issues related to the new items. The Vikings say they’re paying the increased cost of $1.3 million, which bumps the total project budget up to $977 million.

The increased cost covers only design — not the materials, the escalators and the televisions themselves.

The designers will decide what locations are best for the TVs so fans need never miss a Purple play. There is no decision yet on whether there will be TVs in the restrooms.

The authority also discussed potential changes to the stadium related to the 2018 Super Bowl — namely, adding more suites — but no decisions have been made. Authority Chair Michele Kelm-Helgen said the Vikings will cover the costs of any Super Bowl-related stadium changes.

The authority also discussed changes required for an NCAA basketball Final Four tournament. The state is bidding for a 2019 or 2020 Final Four, and if it were to win the bid, Kelm-Helgen said the authority would pay for the necessary four locker rooms.

In other action, M.A. Mortenson Co. provided an update on construction, previewing the arrival of the star attraction of the project: the biggest, tallest crane.

The 375-foot-high crane with a 670-foot reach will start rolling onto the site in pieces later this month from its current assignment in New Florence, Pa. Upon its assembly, the crane will be ready to pick up its first piece of steel July 31. The biggest piece to be hoisted: 600,000 pounds.

John Wood, Mortenson senior vice president, reported that 400 people are now working on the site daily. In total, 100,000 cubic yards of concrete will be poured; so far, workers have poured 17 percent of that, he said.

Wood said through the end of May, $89 million has gone into the site, even though much of it has been in the hole and not visible to the public. Typically, that amount of work takes two years, he said.

 

Rochelle Olson • 612-673-1747

@rochelleolson

  • get related content delivered to your inbox

  • manage my email subscriptions

ADVERTISEMENT

Chicago WSox 7 Top 8th Inning
Detroit 4
Colorado 1 Top 7th Inning
Chicago Cubs 3
St. Louis 4 Top 3rd Inning
San Diego 2
Philadelphia - C. Lee 6:05 PM
Washington - G. Gonzalez
LA Angels - T. Skaggs 6:05 PM
Baltimore - B. Norris
Seattle - C. Young 6:05 PM
Cleveland - Z. McAllister
Cincinnati - J. Cueto 6:10 PM
Miami - T. Koehler
Minnesota - K. Correia 7:10 PM
Kansas City - Y. Ventura
Toronto - D. Hutchison 7:10 PM
Houston - J. Buchanan
Pittsburgh - J. Locke 8:40 PM
Arizona - J. Collmenter
Atlanta - J. Teheran 9:10 PM
Los Angeles - C. Kershaw
NY Giants 8/3/14 7:00 PM
Buffalo
Winnipeg 6:00 PM
Hamilton
Toronto 8/1/14 6:00 PM
Montreal
Brt Columbia 8/1/14 9:00 PM
Calgary
Saskatchewan 8/2/14 6:00 PM
Ottawa
Saskatchewan 8/7/14 7:30 PM
Winnipeg
Edmonton 8/8/14 6:00 PM
Montreal
Hamilton 8/8/14 9:00 PM
Brt Columbia
Ottawa 8/9/14 6:30 PM
Calgary
Atlanta 7:00 PM
Tulsa
Phoenix 7:00 PM
Minnesota
New York 7:00 PM
Chicago
Indiana 9:00 PM
Seattle
Connect with twitterConnect with facebookConnect with Google+Connect with PinterestConnect with PinterestConnect with RssfeedConnect with email newsletters

ADVERTISEMENT

ADVERTISEMENT

Date/Opponent Time W L Score
2014 preseason     
Aug 8 - vs. Oakland 7 pm
Aug 16 - vs. Arizona 7:30 pm
Aug 23 - at Kansas City 7 pm
Aug 28 - at Tennessee 7 pm
2014 regular season     
Sep 7 - at St. Louis Noon
Sep 14 - vs. New England Noon
Sep 21 - at New Orleans Noon
Sep 28 - vs. Atlanta 3:25 pm
Oct 2 - at Green Bay 7:25 pm
Oct 12 - vs. Detroit Noon
Oct 19 - at. Buffalo Noon
Oct 26 - at Tampa Bay Noon
Nov 2 - vs. Washington Noon
Nov 9 - Bye
Nov 16 - at Chicago Noon
Nov. 23 - vs. Green Bay Noon
Nov. 30 - vs. Carolina Noon
Dec 7 - vs. NY Jets Noon
Dec 14 - at Detroit Noon
Dec 21 - at Miami Noon
Dec 28 - vs. Chicago Noon

ADVERTISEMENT

ADVERTISEMENT

ADVERTISEMENT

question of the day

Poll: Which local pro team are you most excited about?

Weekly Question

ADVERTISEMENT

 
Close