Stearns Bank says Duluth Central High School site developer has defaulted on $5.6M loan

The bank defends itself for the first time against claims by developer Lazar “Luzy” Ostreicher that it undermined a crucial project for Duluth.

The Minnesota Star Tribune
July 31, 2025 at 2:48PM
Redevelopment of the land that once housed Duluth Central High School is in limbo after the developer's financial backing fell apart. (Alex Kormann/The Minnesota Star Tribune)

Stearns Bank has fired back at developer Lazar “Luzy” Ostreicher after the developer blamed the St. Cloud lender for the woes of a mammoth Duluth real estate project.

Stearns said this week that Ostreicher’s Incline Plaza Development has defaulted on a $5.6 million loan, giving the bank rights to foreclose on 30 acres of Duluth hillside property.

Stearns made the claim on Tuesday in response to a suit filed against it by Incline Plaza earlier this month. It was the bank’s first public comment on a dispute that has festered for six weeks.

Ostreicher’s project, dubbed Incline Village, was hailed as an economic balm for Duluth. Plans call for over 1,200 residential units — basically a new neighborhood — on 53 acres of land that was once the site of Central High School and had gone undeveloped for years.

Incline Plaza claims Stearns failed to make a critical commitment for the project’s first phase, causing a $45 million financing package to implode.

Stearns says that it never “guaranteed,” as Incline claimed, that it would issue a $27 million letter of credit to backstop the financing.

In December, Stearns Bank representatives joined city officials and Ostreicher at a festive public groundbreaking.

Lazar "Luzy" Ostreicher, second from left, at the December groundbreaking of Incline Village, a $500 million housing project in Duluth. The project is now in limbo. (Jana Hollingsworth/The Minnesota Star Tribune)

But in early June, the Duluth Economic Development Authority (DEDA) concluded that Ostreicher’s companies had breached eight parts of a development agreement.

Key financial information was missing, construction contracts were in default and little work had been done.

DEDA gave Incline Plaza 45 days to cure the contract breach. Incline contested some of the city’s findings and asked for a 120-day extension to fix the problems.

Ostreicher’s companies have invested more than $10 million into the project, including $8 million for the land.

But last week, DEDA voted to terminate the development agreement. By doing so, DEDA axed $75 million in tax increment financing (TIF) for Incline Village.

The project is now in limbo.

Incline Plaza sued Stearns Bank July 3 for breaching a loan agreement and fraud or intentional misrepresentation.

The developer claims that DEDA’s actions “are the direct and proximate result” of Stearns Bank’s failure to transmit the $27 million letter of credit through SWIFT, a global communications system for banks.

Incline Plaza has said “that the bank deliberately or negligently misrepresented” that it was connected to SWIFT and could send the letter of credit.

The letter of credit was supposed to backstop a $45 million equity investment into the project by SGGI Holdings.

Aside from the letter of credit issue, Stearns Bank in November granted Incline Plaza a $5.6 million short-term loan to begin work on the project’s first phase.

The loan helped pay off an existing mortgage that Incline Plaza had on the property, Stearns said in a court filing.

The loan, now in default, is personally guaranteed by Ostreicher and one of his business associates, Eli Leshkowitz, Stearns Bank claims in the lawsuit. The loan also is secured by about 30 acres of hillside land owned by Incline Village, the suit says.

The bank says it is owed a total of $5.8 million, including accrued interest and late charges. It is asking the court for a judgment on loan and the ability to foreclose on the loan.

It’s not clear what happens next with the project.

Incline Village’s construction management firm ICS terminated its contract with Ostreicher on July 3, according to its president, Andy Faulkner.

The company had suspended work June 2 because it had not been paid, but worked with the city to protect the site, which it had been working on for several months. The company still has not been paid, Faulkner said in a statement.

Jana Hollingsworth of the Minnesota Star Tribune contributed to this story.

about the writer

about the writer

Mike Hughlett

Reporter

Mike Hughlett covers energy and other topics for the Minnesota Star Tribune, where he has worked since 2010. Before that he was a reporter at newspapers in Chicago, St. Paul, New Orleans and Duluth.

See Moreicon

More from Real Estate

See More
card image
Provided by AGNT Media

A former Cold War-era missile launch site is among three Minnesota listings with their own “safe rooms.”

iStock
Isometric small house and green dollar sign on weight scales. Balance, price, real estate and home concept.
card image