An unsealed transcript in Minnesota's investigation of a massive cost overrun at Xcel Energy Inc.'s Monticello nuclear power plant is raising questions and controversy about whether the utility's board of directors deserves some of the blame.
In the transcript, a nuclear expert hired by the state said that Xcel directors cut the project budget before any work began, disregarding a recommendation of engineers working on the project, and ordered a "fast track approach" with construction milestones that couldn't be met.
The board's action was among "numerous project risks related to cost issues that, as a whole, points to a dysfunctional project management program, " Mark Crisp, a Georgia-based consultant, said in written testimony that was unsealed at the request of the Star Tribune.
A top Xcel executive said Friday that the claims about board missteps are wrong, even though Crisp based them on a company memo describing early problems with the project.
"That is flat-out inaccurate," Laura McCarten, a regional vice president for Xcel, said of the testimony about the board.
The investigation by Minnesota utility regulators is looking at Xcel's handling of the five-year project to replace 1960s-era equipment, including the turbine and major pumps, to extend the Monticello plant's life and boost output. Construction costs more than doubled to $665 million from the original estimate, and now regulators must decide whether Xcel's investors or its 1.2 million Minnesota customers should absorb all or part of the extra expense.
The previously sealed testimony about the board, along with an internal Xcel memo on which the testimony is based, were released this week after the Star Tribune requested them and Xcel dropped most of its claims to trade secrecy.
The newspaper on Wednesday reported that the state investigation had largely faulted Xcel's management for spiraling costs. Investigators concluded that Xcel managers didn't understand or fully plan for the complex job of replacing major reactor components, didn't adequately oversee contractors and misleadingly blamed the U.S. Nuclear Regulatory Commission (NRC) for some of the costly delays.