Unpaid bills, cost overruns alleged at Prairie Island nuclear plant

A North Carolina contractor said Xcel refused to pay cost overruns in a project at the Prairie Island nuclear power plant in Red Wing.

November 18, 2014 at 5:16PM
One of the nation's top power plant contractors is alleging $45 million in unpaid cost overruns during Xcel Energy's 18-month overhaul of its Prairie Island Nuclear Power plant in Red Wing, Minn.
One of the nation’s top power plant contractors is alleging $45 million in unpaid cost overruns during Xcel Energy’s 18-month overhaul of its Prairie Island Nuclear Power plant in Red Wing, Minn. (Brian Wicker — Star Tribune file photo/The Minnesota Star Tribune)

One of the nation's top power plant contractors is alleging $45 million in unpaid cost overruns during Xcel Energy Inc.'s 18-month overhaul of its Prairie Island nuclear power plant in Red Wing, Minn.

Babcock & Wilcox Nuclear Energy, a Charlotte, N.C.-based contractor, says in a lawsuit filed Wednesday that Xcel has refused to pay the full cost for the complex job of replacing a pair of massive steam generators at the plant's Unit 2. The project was completed last December.

Xcel told Minnesota regulators the project cost $285 million. If the $45 million in disputed charges are added to that, it represents a 16 percent cost overrun.

That's far short of the massive cost overrun on another upgrade project at the Xcel's nuclear power plant in Monticello, Minn. In that project, also completed last year, Xcel admits that costs more than doubled to $665 million. State regulators still are investigating whether the additional expenses were justified.

Xcel generally does not comment on specifics of pending litigation, spokeswoman Mary Sandok said. In an e-mail, Sandok said the Prairie Island lawsuit is solely about claims for additional payment that the company considers without merit. Xcel will file a response within 20 days, she said.

Babcock & Wilcox also alleged that Xcel officials have not told the full story about Prairie Island costs to utility regulators during rate increase proceedings in Minnesota and Wisconsin, where the plant's electricity is consumed. The suit said that Xcel's claim to Wisconsin regulators that the project stayed closed to original costs appears to be "disingenuous and in bad faith."

The suit was filed in Goodhue County District Court, and names as a second defendant the project's prime contractor SNC-Lavalin Nuclear Inc., based in Pittsburgh. SNC hired Babcock & Wilcox as a major subcontractor. The lawsuit suggests that Babcock's main complaint is with Xcel because SNC submitted the subcontractor's billings to Xcel, which then refused to pay.

The suit alleges breach of contract, unjust enrichment and seeks to enforce a mechanic's lien filed on the power plant's property in July. Such liens are more commonly associated with smaller disputes over building construction where subcontractors have gone unpaid. The suit claims interest on unpaid bills of $22,000 per day.

SNC-Lavalin declined to comment as did Babcock & Wilcox and its Minneapolis law firm, Fabyanske, Westra, Hart & Thomson. The Minnesota Public Utilities Commission Wisconsin Public Service Commission, through spokesmen, said they would not comment.

Major construction project

The replacement of the 40-year-old steam generators at Prairie Island was a major project, employing up to 1,500 workers for more than a year. The 330-ton generators were assembled in France, arrived by ship and barge, and were hoisted through a hatch in the containment building with only inches of clearance.

According to the lawsuit, Babcock & Wilcox's contract contained both fixed and "target" prices. The latter are estimates and required Xcel to pay the actual costs, the suit said. Some of the higher costs, the suit contends, grew out of Xcel's decision to perform additional work of its own at the same time, causing delays by interfering with movement of Babcock workers and equipment in the plant.

Babcock & Wilcox contends that much of the work was done in cramped places where workers must put on and take off radiation protection gear every time they passed through a portal. In arguing that its charges were justified, the company's lawsuit quotes statements from Xcel officials defending the cost of the Monticello nuclear power plant upgrade. That project also required work in tight, radioactive areas of the plant.

The cost of the Monticello upgrade, which replaced decades-old equipment and boosted the plant's output, is under review by an administrative law judge, who will issue findings later this year. If regulators decide some of costs were imprudent, Xcel's investors will take the financial hit, sparing customers from at least a portion of the utility's next rate hike.

David Shaffer • 612-673-7090 Twitter: @ShafferStrib


Terry Pickens, director of nuclear regulatory policy for Xcel Energy walked by one of two steam powered generators at the plant. Steam is heated in the nuclear vessel. The Xcel Energy Prairie Island Nuclear Plant north of Red Wing is looking to boost electrical output at the plant. Tuesday, October 9, 2012 ] GLEN STUBBE * gstubbe@startribune.com ORG XMIT: MIN1210091609103007 ORG XMIT: MIN1303271624141706
Xcel has been sued over an alleged $45 million in unpaid cost overruns of the Prairie Island nuclear power plant project. (The Minnesota Star Tribune)
The two oldest heat-conversion units in the U.S. nuclear power industry are about to be replaced at a cost of $285 million at Xcel Energy's Prairie Island reactors in Red Wing. The steam generators are key parts of pressurized-water reactors, converting hot, radioactive fluid from the reactor core into non-radioactive steam to drive turbines. The twin 330-ton replacement units, built in France, rely on nearly 3,400 tubes -- perhaps the weakest link in the technology -- to transfer the heat.] Ric
The nuclear plant in Red Wing was overhauled by Xcel. (The Minnesota Star Tribune)
about the writer

about the writer

David Shaffer

Reporter

See Moreicon

More from Business

See More
card image
Fairview Health Services

The school is changing an elective course while still working with the Eden Prairie-based health care giant after students raised concerns.

This transmission electron microscope image shows SARS-CoV-2, the virus that causes COVID-19, isolated from a patient in the U.S., emerging from the surface of cells cultured in the lab. (NIAID/TNS) ORG XMIT: 1659810
card image