Xcel Energy workers cut underground cables that caused a monthslong outage at its Prairie Island nuclear power plant, and now the energy company wants customers to pay most of the costs for that mistake.
For now, that tab is north of $23 million for the cost of energy bought on the open market to replace the lost nuclear power in 2023. Gov. Tim Walz’s administration and Attorney General Keith Ellison, however, say the responsibility of shouldering the bill should fall on Xcel shareholders instead.
“Xcel’s failure to manage its contractors fell far below what is expected of a reasonable and prudent nuclear plant operator,” read a regulatory filing Assistant Attorney General Peter Scholtz signed. “The Company’s ratepayers should not have to pay for the results of its imprudent conduct.”
The Minnesota Public Utilities Commission (PUC) will decide whether to refund any costs to customers, though the five-member board is still taking input on the issue and hasn’t scheduled it for a vote yet.
The price for replacement power for the outage at Unit 1 and Unit 2 in 2023 was about $33.8 million, according to the Minnesota Department of Commerce, but data the state agency released showed the company also saved an estimated $10.3 million by not running the plant, lowering the overall cost.
The full price tag for the incident will be higher, though, as Xcel hasn’t calculated replacement power costs from 2024 yet. The company also plans to ask for customers to bear $9 million to $12 million for cable repair, building that into its next electric rate case.
Xcel acknowledged it caused the outage. Workers cut through a bundle of cables, interrupting power to some equipment and causing one of two reactors at the Red Wing plant to shut down. The company told federal nuclear regulators it did not use ground radar in an area that would have shown the cables’ location and admitted its excavation planning and oversight was inadequate.
Still, Xcel argued it should not have to refund to customers those extra energy costs because it was operating prudently and in good faith despite the unintentional outage. Those workers were helping with an unrelated cable replacement project at the time, maintenance that Xcel said was necessary.