MONTICELLO, Minn. – A major upgrade to Minnesota's oldest nuclear power plant is finally finished — and way over budget.
Xcel Energy expects to restart its Monticello Nuclear Power Plant this week after a four-month shutdown that allowed workers to replace aging pumps and other equipment to keep the 43-year-old reactor running another two decades and to boost electric output by 12 percent.
But the cost of the work surged $267 million, or 83 percent, over its 2008 budget of $320 million. The Minneapolis-based electric and gas utility says the final costs will be even higher, but hasn't publicly disclosed the amount.
In the meantime, Xcel's 1.2 million electric customers in Minnesota are being asked to pay for the cost overruns. This sort of nuclear-related expense is one of the major drivers behind Xcel's requested rate hike that an administrative judge recently recommended slashing to 4.7 percent. The Minnesota Public Utilities Commission will decide, probably this fall, how much more ratepayers will pay.
Utility officials declined to answer questions about the cost overruns, saying it would be inappropriate to comment while state regulators are considering the rate hike request. In regulatory filings, Xcel has defended the cost increase for upgrading the Monticello plant, citing schedule changes, vendor issues, evolving regulations and unexpected work. Xcel promised additional explanations later.
"[It] is a large, complex project with many intricate components that required changes from original plans," Xcel's chief nuclear officer, Timothy O'Connor, said in recent written testimony submitted to state regulators.
Such cost overruns are further proof of the "very dicey" economics of nuclear power, said Mark Cooper, a senior research fellow for economic analysis at Vermont Law School's Institute for Energy and the Environment.
"They cannot build these things or repair them or expand them without having severe cost overruns and that is part of the technology," Cooper said in an interview.