The company trying to resurrect the former Essar Steel Minnesota site in Nashwauk faces penalties worth millions after it missed a key state deadline to begin construction on a promised, high-end iron ore processing plant.
Mesabi Metallics was supposed to start construction on one of the Iron Range site's facilities by Dec. 31, 2018, but an inspection by the Department of Natural Resources (DNR) found that work had not been done, said Barbara Naramore, the DNR's assistant commissioner.
"Under the terms of the state mineral leases, failure to meet this deadline results in a doubling of rents and royalties due to the state," she said. "We have notified Mesabi Metallics of the schedule under which these increased payments are due."
The rents will double to $120,000 each quarter. By the end of 2019, full-year royalties and rents will now be a total of $12 million.
Mesabi acknowledges that the work on the "value-added" facility adjacent to the half-built pelletizing plant was not completed by the deadline, said spokesman Darin Broton.
However, he said those deadlines were made by a former management team and before Mesabi faced litigation and other issues came into play.
The company hopes to discuss the payments with the DNR in more detail in the coming weeks and show what design and engineering work has been completed on the "value-added" high-grade ore facility. That plant is expected to be built adjacent to a half-built taconite pelletizing plant that Mesabi also hopes to complete.
Broton said Mesabi has submitted a new construction timetable to the DNR but still hopes to finish the whole $2.6 billion project by the end of 2019.