The dirty, noisy and disruptive construction work on the Central Corridor light-rail line between St. Paul and Minneapolis will end completely by the end of the month, spelling relief for many businesses and commuters.
With new streets and sidewalks laid, store owners are grappling with how to rebound from months of snarled traffic that sapped their business.
"We're relieved," said Ne Dao, owner of Ha Tien Market on University Avenue near Western Avenue. The market and deli lost about half of its daily business, forcing Dao to cut employees' hours, stop ordering dry goods inventory and halve the store's fresh produce orders. Three employees quit.
Customers found it difficult to find the store amid the clogged traffic, she said. And when they did, finding a place to park was difficult after on-street parking was eliminated. "[Customers] told me they drove by four or five times and they couldn't get in," Dao said.
Putting the finishing touches on the $957 million project next year should be far less disruptive to businesses and commuters, said Mark Fuhrmann, program director of New Starts rail projects for Metro Transit. Crews will string miles of overhead electrical wires and underground cable, install station art, build the operations and maintenance facility in St. Paul's Lowertown, work on the signaling and communications system and test the light-rail vehicles. The rail line along the 10-mile corridor is expected to be open for business in 2014.
Work on the project in 2012 went more smoothly than the previous year after changes were made to minimize the length of disruptions and better inform businesses about them, Fuhrmann said.
For example, much of the work in 2011 was done in one-mile increments. But the contractor sometimes didn't have the equipment or crews to handle it, Fuhrmann said. "So you had areas where they tore off the pavement and then they disappeared for one or two weeks," he said. "That wasn't well received."
This year, crews worked on shorter segments of five to six blocks, Fuhrmann said.