The decision to delay the Twin Cities' biggest light-rail project drew protests and warnings Wednesday from two policymakers who have been closely involved in planning the line.
They objected to postponing a crucial vote on whether to build two tunnels as part of the Southwest Corridor line that will connect Minneapolis with Eden Prairie and southwestern suburbs. The delay of as much as three months is intended to give planners time to build support for the tunnels in Minneapolis, where some officials and residents fear disruption to a neighborhood and a recreation area.
"This is going to be a huge setback," said Steve Elkins, a member of the Metropolitan Council, the agency overseeing the project.
"A delay means that the project could be at risk," said Council Member Jennifer Munt. "Does this derail the project?"
Elkins and Munt fear the delay could cost the $1.55 billion project its best chance to win needed federal funding.
But a majority of Met Council members Wednesday joined Chairwoman Susan Haigh in endorsing Gov. Mark Dayton's call for planners to conduct more studies on the tunnels' environmental impact and to explore alternatives.
Dayton announced his support for a 60- to 90-day delay Tuesday after a closed-door meeting with Haigh, Minneapolis Mayor R.T. Rybak and key legislators. Citing opposition in Minneapolis, Dayton said "we need to step back and everybody take a deep breath." The Met Council is required to ask Minneapolis and the four other cities along the light-rail route for their consent before proceeding with construction work.
The $160 million tunnel plan involves burying two sets of tracks beneath the Kenilworth corridor of Minneapolis. The trains would surface for about 20 seconds when crossing a bridge over a water channel between two lakes.