Met Council stadium report highlights

October 13, 2011 at 2:26AM

Cost of delay• Cleanup of state's largest Superfund site has significant uncertainties

• Aggressive schedule (2015) is unrealistic

• Cost of a one-year delay -- $46 million

Unfunded cost gap

• $39 million of project costs not identified in $1.111 billion proposal

Ramsey County sales tax

• Proposed .5% tax may compromise financing for other projects

about the writer

about the writer

More from No Section

See More
FILE -- A rent deposit slot at an apartment complex in Tucker, Ga., on July 21, 2020. As an eviction crisis has seemed increasingly likely this summer, everyone in the housing market has made the same plea to Washington: Send money — lots of it — that would keep renters in their homes and landlords afloat. (Melissa Golden/The New York Times) ORG XMIT: XNYT58