The November launch of a new kind of bus transit on Cedar Avenue is looking less and less likely.
Dakota County commissioners heard Tuesday that some key elements of the bus-rapid transit (BRT) project -- most notably, two of its five stations -- will not be finished in time, probably pushing the full launch into 2013.
The busway from Apple Valley to Bloomington is meant to mimic light rail, with sleek buses running in dedicated shoulder lanes with regular stops at roadside stations.
The County Board, amid some contentious debate, stopped short of declaring a delay and urged its staff to get as much as possible done by November.
A STATION DILEMMA
Most pressing is construction of two "walk-up" stations in Apple Valley at 140th and 147th Streets, but there's disagreement on what they should look like.
Apple Valley city officials, who ultimately will need to issue building permits, want skyways connecting the platforms on either side of the road. The county and the Metropolitan Council have said there won't be enough ridership at first to justify that cost.
Even if everyone can promptly agree on design, it will be early 2013 before the stations are built.
MANY MOVING PIECES
The checklist of tasks related to Cedar Avenue is long and complicated.