The high point of the prow is in place. The concrete scissor ramp has been poured. The loading dock leads under the building from the street. The steel skeleton snaps into place more each day on the $1 billion NFL stadium going up in downtown Minneapolis.
Down in the dirt pit of the stadium construction site on Monday afternoon, the heavy equipment beeped steadily from all directions, an audible signal of the constant movement of concrete and steel by some 650 workers on a finely calculated path toward opening day in 2016.
M.A. Mortenson Co. and the Minnesota Sports Facilities Authority took two dozen reporters on the first hard-hat tour of the project since demolition of the Metrodome in January gave way to the $1 billion structure's rise from the ground.
From the street, it's a marvel of synchronicity. Up close, it's all bigger and dustier.
On what will become the 50-yard line lie the solid oak tracks to support the massive crawler crane brought on site to lift the heaviest chunks of steel that will form the building's roof.
The biggest piece, a 740,000-pound ridge, currently lies in the dirt, awaiting its mid-November date with the crawler crane. The crane will hoist the ridge piece into place, where it will eventually form the backbone of the roof.
Cranes are the key. Construction manager Dave Mansell says it's about "maximizing hook time" right now. Most everything at the site needs to be lifted and set down.
Cranes operate from early morning until past midnight, providing the synchronicity required to keep everyone on the site working toward the finish date. "We can't be going backwards out there," Mansell said, adding that the construction schedule is on a "zero float path" with no room for delay.