Construction is scheduled to begin next year on a strategic connection in Washington County's growing network of recreational trails.
The Point Douglas Regional Trail, the first major trail in the county's south end, will link two bridges over two rivers in two states. Cyclists and pedestrians will be able to cross the Mississippi River bridge to downtown Hastings, where they can connect with Dakota County trails. They will also be able to cross to the east, over the St. Croix River bridge to downtown Prescott, Wis.
Someday, the Point Douglas trail also will link to a new St. Croix Valley Trail that would run north to Afton, Bayport and Stillwater.
"It's really an important link between a variety of trail systems," John Elholm, the county's parks director, said of the $3.4 million trail.
The 2½-mile path — built on an abandoned railroad corridor — will run along the south side of U.S. Hwy. 10 in Denmark Township and the small portion of Hastings that is located in Washington County.
The county, which has been buying land to complete the route, most recently acquired property to build a safe connection to where the trail will follow heavily traveled Hwy. 61 north of the Hastings bridge.
In its most recent action involving the project, the Washington County Board voted to hire Stonebrooke Engineering of Burnsville to design a pedestrian bridge that would be built over two tracks used by the BNSF Railway.
The county's timetable shows that all land for the Point Douglas trail will be acquired by March. The trail design will be completed by May and the pedestrian bridge design by next fall. It will solicit bids for construction next winter, with work beginning in April 2016.