The construction manager of the new U.S. Bank Stadium isn't owed $15 million for extra work at the new Minnesota Vikings facility, according to a legal document released Friday by the Minnesota Sports Facilities Authority.
The 22-page document is the MSFA's answer to M.A. Mortenson Co.'s Aug. 5 request to enter mediation over $15 million the company claims it is owed for work on the stadium because of changes to the original designs.
For example, Mortenson's initial filing, also released Friday, said that in November 2013, when Mortenson set the guaranteed maximum price for the project, the MSFA's stadium design called for two main electrical feeders into the building. In the final construction document of May 2014, that was still the plan, but in August last year, the MSFA ordered a third electrical feeder.
Mortenson has thus far unsuccessfully sought a $1 million payment for that change. The company says it required a subcontractor to rip out existing work to lay the third feeder. In response, the MSFA says that paying the money would cause the cost to exceed the "guaranteed maximum price" set by Mortenson in its bid.
MSFA Chair Michele Kelm-Helgen said at Friday's regularly scheduled board meeting that she hoped for a speedy resolution to the dispute. Both she and Mortenson Senior Vice President John Wood said at the meeting that the process has been cordial despite the disagreement. Wood emphasized that the $1.1 billion building is precisely on schedule to be completed in 10 months.
Part of the authority's argument against paying the claims is that Mortenson didn't properly submit documents or follow prescribed procedures.
The MSFA issued a statement regarding its filing saying cost disputes on such a large project are common and it remains "committed to building the best facility."
Wood said in an interview, "What we're dealing with is a fundamental difference of opinion about the interpretation of the contract with regard to changes."