For the Gophers, the wait to begin construction on new football and basketball practice facilities just got longer.
Athletics department officials hoped the Board of Regents could use next week's meeting to approve a long-awaited $150 million athletics facilities project, setting up an August groundbreaking.
But Friday, the university announced that the Regents won't vote on the project until their September meeting.
School officials said the three-month wait for the vote won't delay the project from being completed by the summer of 2017. But it will push the groundbreaking to at least mid-September, extending uncertainty for recruits.
"Do I want it started in August? Darn right. I've said that all along," Gophers football coach Jerry Kill said. "But at the same time, if you wait a month to make sure you have all the schematics right, then you don't have to change something midstream."
The university first unveiled plans for a $190 million "athletics village" in July 2013, with upgrades for several teams. In January, the school streamlined a $150 million portion of the project, fast-tracking the football and basketball facilities, along with a nutrition and academic center that will serve all 720 of its athletes.
So far, $70 million has been raised, with the university still committed to fundraising all the money. Last month, athletic director Norwood Teague said the department was "getting down to the wire" on some significant gifts, adding that he was planning on an August groundbreaking, pending Regents approval.
Teague was unavailable for comment Friday, but senior associate AD Chris Werle said the delay wasn't money-related.