Cost overruns in Washington County public works projects came under scrutiny last week when some elected commissioners said they were having trouble explaining price changes to constituents.
"There have been some projects where, when change orders happened, it wasn't explained very well or communicated very well," said Karla Bigham, the newest commissioner. "It seems like there's recurring things that always have cost overruns. Is there a way to do more due diligence on the front end?"
County Engineer Wayne Sandberg responded that cost overruns — called "change orders" in county language — are common in construction as contractors uncover new challenges and the public wants additional improvements.
"Never is there a situation where we deliver all the unknowns in construction," Sandberg told the county's five commissioners in an informational workshop. "Typically, it's because we want more work or different work than the original scope. That's the most common scenario."
In 36 highway construction projects since 2011, the total cost of original bids was $72.1 million. according to county records. Changes in contracts resulted in a total additional cost of $5.5 million, a bit more than a 7 percent increase.
Thirteen of those 36 projects saved $371,922 less than the original bids.
"I think there's a lot lost in translation as a major project rolls out," said Gary Kriesel, the County Board's longest-serving member. "We have to have a better way of communicating where we're at and why we're there. We've got to have a process in place that takes us from initial concept, that commissioners as well as citizens can look at things, and dots are connected."
Bigham said that in her district, which includes Cottage Grove, "we've had some projects lately where there have been some issues." One of those was a roundabout project on 70th Street, and another was at the Newport Transit Station where poor soils were discovered during construction, she said.