On a scorching day in June 2013, the Grand Canyon discouraged hikers from making a long trek to the bottom because there would be no potable water. A set of historic cabins and bunks also would be closed overnight because of a water pipeline break.
The incident was one of more than 85 breaks that the 12.5-mile (20-kilometer) long Transcanyon Waterline, which supplies potable water to the Grand Canyon's South Rim and inner canyon, has experienced since 2010. Finished in 1970, the pipeline has long exceeded its 30-year design life, disrupting operations at one of the most popular U.S. national parks.
The pipeline has remained a leaky, flimsy albeit vital piece of infrastructure for millions of visitors. This year, after multiple breaks, officials imposed water restrictions and canceled overnight stays at busy hotels, upending some summer vacations over Labor Day weekend.
A long-term fix is expected by roughly 2027, but it's taken decades to get to that point. The lengthy timeline is due to a complex design process and the challenge of funding expensive projects at the National Park Service, which struggles under mountains of overdue maintenance, according to experts who know its history.
''It just takes awhile for something this big,'' said Robert Parrish, chief of planning, environment and projects at Grand Canyon National Park, adding that it's not just the park service — utilities can take 10 to 15 years to start building big projects.
Recent stays at El Tovar Hotel, Bright Angel Lodge and other hotels on the canyon's South Rim were halted for roughly a week as officials rushed to patch up four breaks in the water line.
The Transcanyon pipeline twists and turns over the canyon's rugged terrain. For years, the park service repaired pipeline failures from rock falls, freezes, flash floods and other causes on an ad hoc basis, Parrish said. One 2015 estimate said over roughly the previous three decades, the pipeline suffered five to 30 breaks per year. Those cost on average about $25,000 each.
It isn't like fixing most pipelines, according to Dan Cockrum, chief of maintenance and engineering at the park for nearly a decade until 1993.