Vikings find $975M isn't enough for everything in new stadium

  • Article by: RICHARD MERYHEW , Star Tribune
  • Updated: October 10, 2013 - 6:38 AM

As groundbreaking nears on a new stadium, the team finds it may have to trim some amenities like a parking garage and a skyway.

hide

The new Vikings stadium, shown in an artist's rendering.

 

Even before the first chunk of earth is turned for the new Vikings’ stadium, project planners are finding out that $975 million doesn’t go nearly as far as they had hoped.

Officials for the team and public authority overseeing construction have been forced to trim their project wish list to keep the downtown Minneapolis stadium within budget.

Among the potential casualties: a 400-stall parking garage a block north of the stadium, a skyway linked to a ramp a block south, two large escalators and as much as 40 feet from the height of five massive, pivoting glass doors at the venue’s main entrance.

“We only have $975 million in the budget, and there’s only so many things you can get under that number,” said Vikings Vice President Lester Bagley.

Michele Kelm-Helgen, chairwoman of the Minnesota Sports Facilities Authority, the project developer, said an uptick in the construction industry and pressures on an already tight construction workforce have pushed some preliminary bids on the project higher than anticipated.

As of last week, the bids had exceeded the budget by $20 million to $30 million, forcing the team and authority to do some “value engineering” and make tough choices on what they could possibly live without, she said.

“It’s all moving around,” Kelm-Helgen said, adding that the two sides are continuing to work with the stadium builder, Mortenson Construction, to price out the work before Mortenson delivers a guaranteed maximum construction price by November, in time for groundbreaking.

“These were just preliminary bids. That doesn’t mean those bids will necessarily hold. But we’re continuing to negotiate and work those numbers. At this point, we’re in budget.”

Dan Kenney, executive director of the Minnesota Ballpark Authority, which worked with the Twins to build Target Field, said early challenges in managing a project budget are not unusual.

“They are in a place where every project is at,” Kenney said of the stadium authority and Vikings.

“As you get deeper into the design detail, you can get better estimates on what it is you are actually buying. Once the bids come in, you have to make adjustments. And yes, some things come in higher than anticipated. You just need to work through that.”

Kenney said that Target Field’s original design called for building a restaurant beyond center field. To save costs, the idea was scrapped, allowing the team and authority to add more outfield seats.

The Twins also invested an additional $65 million to construction, increasing their commitment from $130 million to $195 million.

Contingency funds

The authority and Mortenson have set aside more than $62 million in contingency funds that could be tapped to restore some of what’s been cut if the money isn’t spent to cover unforeseen construction issues, such as major soil cleanup or shipping delays.

The Vikings also have agreed to advance $13.1 million to restore some features on their wish list that had been targeted for cuts, including installation of a Wi-Fi system. The team would recoup the investment at the end of construction if contingency funds remain.

“We want to make sure we have that first-class facility,” said Don Becker, who helped negotiate the development agreement for the Vikings. “We know there are things that we want to include in this building and we consider them ‘must haves.’ ”

  • get related content delivered to your inbox

  • manage my email subscriptions

ADVERTISEMENT

Connect with twitterConnect with facebookConnect with Google+Connect with PinterestConnect with PinterestConnect with RssfeedConnect with email newsletters

ADVERTISEMENT

ADVERTISEMENT

ADVERTISEMENT

ADVERTISEMENT

ADVERTISEMENT

 
Close