Continued: Xcel Energy wants a do-over in Plymouth

  • Article by: TOM MEERSMAN , Star Tribune
  • Last update: January 25, 2014 - 6:57 AM

Xcel has advanced other transmission line proposals in the west metro, including an 11.4-mile stretch of new and upgraded line between eastern Carver and northern Scott counties that goes through downtown Chaska.

State to decide

Before Xcel can start over to come up with a different proposal in Plymouth, the utility needs state approval to withdraw its first project. The touchy question of whether to attach conditions to any new plan is now before the state Public Utilities Commission, with a public comment period deadline of Jan. 29.

The commission is unlikely to decide the matter until spring, and Alders said it’s not clear how long after that it will take for Xcel to come up with an alternate project.

For McBride, any proposal that contains a new or upgraded power line will not be acceptable.

“There is no immediate need for a high-voltage transmission line,” she said. “Maybe that day will never come because of new technology or new efforts at conservation. There’s no need to destroy the value and enjoyment of people’s homes.”

 

Tom Meersman • 612-673-7388

  • get related content delivered to your inbox

  • manage my email subscriptions

ADVERTISEMENT

Connect with twitterConnect with facebookConnect with Google+Connect with PinterestConnect with PinterestConnect with RssfeedConnect with email newsletters

ADVERTISEMENT

ADVERTISEMENT

ADVERTISEMENT

ADVERTISEMENT

ADVERTISEMENT

question of the day

Poll: How will the Vikings do against Atlanta?

Weekly Question

ADVERTISEMENT

 
Close