MnDOT doubted a plan to bolster bridge

A consultant urged new plates for the aging I-35W bridge, the same plates that are now the focus of a federal inquiry, records show.

2bridge1018.jpg
hide

Officials last month examined the L-11 section of the I-35W bridge wreckage at the NTSB's secured downstream site in Minneapolis.

In the year before the Interstate 35W bridge collapse, the engineering firm that studied the structural safety of the bridge found itself at odds with state transportation officials as it pushed a plan to reinforce the aging structure.

According to newly released documents from the Minnesota Department of Transportation, consultant URS Inc. played a diminishing role in decisions about the bridge even as it prepared its final report on its maintenance.

The records also show that URS was puzzled when MnDOT suddenly cast doubt on the consultant's $2 million plan to strengthen the bridge with steel plates.

The documents -- a mix of 13,500 e-mails and other communication from 2003 through 2007 -- offer the most complete look yet at the partnership between MnDOT and the San Francisco-based consultant, which had spent three years doing computer modeling and analysis on the 40-year-old bridge.

The Star Tribune obtained the documents through a state data practices act request.

In the days after the collapse, MnDOT said state officials and URS had mutually decided to explore other options instead of bolting steel plates to bridge sections at risk of cracking. But the documents indicate the two sides had a substantive disagreement over how to proceed.

Last December, after pushing for months to replate the bridge, URS abruptly moved closer to MnDOT's position of finding a less intensive way to ensure the bridge's structural integrity. Three weeks after a top URS official had reiterated that the chance of a bridge truss failure "should be significantly reduced" by the replating, the same official suddenly e-mailed a colleague that he no longer thought the replating was necessary.

Even the agreed-upon solution -- closer inspections -- did not proceed as URS expected. On July 19, two weeks before the bridge collapsed, URS official Don Flemming was caught by surprise when MnDOT inspected the bridge without the firm. "I saw them on the bridge, and asked if we were not going to get involved," wrote Flemming, who for 14 years had been the state's bridge engineer before being hired by URS.

MnDOT spokesperson Lucy Kender said in an e-mail that it was "completely erroneous" to conclude that the relationship between the agency and its consultant had deteriorated. A spokesman for URS declined to comment.

Analysis 'very well done'

MnDOT has said it based its decision to postpone the replating because of URS' concerns that the work could actually weaken the bridge. According to the documents, however, URS did not raise this concern when it recommended the replating in the fall of 2006. Nor do the documents indicate that URS was focused on the integrity of the bridge's gusset plates.

Federal investigators have a "working theory" that the bridge collapsed in part because of the failure of gusset plates, which connected the bridge's girders.

"It is true that we don't have much safety margin for local stresses but on the other hand the overall stability of the structural system is not easily to be jeopardized," URS wrote as the company finished a draft report a year before the collapse. In handwritten notes from a September 2005 consultants' meeting, a URS official wrote that "gusset plate buckling -- if this occurs, it is not catastrophic."

From the start, URS executives were eager to do an exemplary job on their contract with MnDOT to evaluate the 35W bridge.

"I view this project as an important opportunity for us to get more work of this type from MnDOT in the future," Ed Zhou, a senior URS structural engineer, wrote in 2003. "This bridge will need deck replacement and rehabilitation."

For more than two years, URS consistently said that the bridge needed a major steel replating, according to the documents. That changed in a matter of weeks late last fall.

In the summer of 2006, URS formally recommended the replating project in its draft final report on the 35W bridge. MnDOT bridge design engineer Kevin Western told the consultant in an e-mail that "in general, the report and analysis was very well done."

At the same time, MnDOT raised concerns about the report's main recommendation.

  • related content

  • Graphic: NTSB focus

    Wednesday October 17, 2007

    NTSB investigators probing the collapse of the I-35W bridge have brought special focus to a...

  • 35W bridge flushes plumbing firm's home

    Saturday November 10, 2007

    Frank's Plumbing becomes the latest I-35W business casualty. Tons of porcelain fixtures must go to make way for contractors.

  • Another $195 million for bridge clears one hurdle, faces another

    Friday November 9, 2007

    Funding for the I-35W bridge passed another hurdle in Congress on Thursday night as House and Senate negotiators approved a $50.9 billion transportation bill, which includes $195 million in emergency...

  • get related content delivered to your inbox

  • manage my email subscriptions

ADVERTISEMENT

Connect with twitterConnect with facebookConnect with Google+Connect with PinterestConnect with PinterestConnect with RssfeedConnect with email newsletters

ADVERTISEMENT

ADVERTISEMENT

ADVERTISEMENT

ADVERTISEMENT

ADVERTISEMENT

question of the day

Poll: Can the Wild rally to win its playoff series against Colorado?

Weekly Question

ADVERTISEMENT

 
Close
2bridge1018.jpg