In about-face, Pawlenty backs an LRT-ready bridge

  • Article by: ROCHELLE OLSON , Star Tribune
  • Updated: August 17, 2007 - 11:44 PM

It would take an estimated extra $20 million to $30 million, but that might be a price worth paying, the governor said.

Gov. Tim Pawlenty said Friday the state may be willing to pay the extra $20 million to $30 million it would cost to include light-rail transit on the Interstate 35W bridge.

Pawlenty's comments came after nearly two weeks of debate and division among state, Minneapolis and federal officials over whether the replacement for the collapsed span should be built with the potential to carry light rail.

Before Pawlenty's comments, Minneapolis officials modified their stance, saying the bridge should have light-rail capacity but need not be built specifically for the Central Corridor line, which is to connect downtown Minneapolis and St. Paul. The city's role could be pivotal because, under state law, it will be asked to provide "municipal consent" for the bridge design.

A disagreement over light rail could stall the project for months, jeopardizing the state's plans to push for completion by the end of 2008.

In Pawlenty's strongest statement of support for light rail since the bridge collapse Aug. 1, he said Friday on his weekly radio show: "It does appear from an engineering standpoint, we can build the bridge ... to be LRT-capable. I've sent signals to the mayor, and he's signaled back that the LRT piece is a significant consideration."

Pawlenty was referring to Minneapolis Mayor R.T. Rybak.

Rybak has pushed to have light rail on the new span. Its price tag without light-rail readiness is estimated at $250 million or more.

The Republican governor has been less enthusiastic about transit than the DFL mayor.

Pawlenty spoke just minutes before the Minneapolis City Council unanimously adopted a set of principles for the new bridge that include making the structure ready for light rail and bus-rapid transit.

Gubernatorial spokesman Brian McClung said the estimated extra cost of making the bridge LRT-ready is between $20 million and $30 million. McClung said the governor's office would ask the Legislature for bonding authority for the money.

Sen. Steve Murphy, the Red Wing DFLer who is chairman of the Senate Transportation Committee, called Pawlenty's comments on light rail "a huge step in the right direction," and he expressed optimism that the $20 million to $30 million could be found.

Rep. Alice Hausman, chairwoman of the House Capital Investment Committee, reacted positively to the potential funding request.

"I think there is just this universal feeling that if we're looking out 100 years, the bridge should be designed and built to specifications that would allow for transit in the future," the St. Paul DFLer said, adding that legislators from throughout the state are hearing a similar sentiment from constituents.

Last week's letter is dead

Rybak and Pawlenty have had differences on the issue almost since the bridge collapse. At a joint news conference Aug. 7, Pawlenty said he'd give "due diligence" to studying transit on the bridge.

But he also signaled that the bridge must be built expeditiously.

Rybak made it clear he wanted the potential for a rail line on the span built to endure for the next 100 years.

On Friday, Rybak called Pawlenty's LRT comments "major" and a welcome shift from even a week ago.

  • get related content delivered to your inbox

  • manage my email subscriptions

ADVERTISEMENT

Connect with twitterConnect with facebookConnect with Google+Connect with PinterestConnect with PinterestConnect with RssfeedConnect with email newsletters

ADVERTISEMENT

ADVERTISEMENT

ADVERTISEMENT

ADVERTISEMENT

ADVERTISEMENT

question of the day

Poll: Do you like the Twins' offseason moves so far?

Weekly Question

ADVERTISEMENT

 
Close