2 companies, Idaho city agree to clean up site of former wooden utility pole treatment plant

Last update: November 10, 2009 - 12:37 PM

BOISE, Idaho - The U.S. Department of Justice says two companies and the city of St. Maries, Idaho, have agreed to clean up creosote left at the site of a former wooden utility pole treatment plant.

The Justice Department and Environmental Protection Agency announced the deal with St. Maries, Carney Products Co. and B.J. Carney & Co. on Tuesday. It was filed in Boise's U.S. District Court late Monday.

Cleaning up the superfund site is expected to cost more than $12 million.

The federal agencies said B.J. Carney & Co. owned the plant from 1960 through the early 1980s, demolition buildings on the site and re-grading creosote-contaminated soil. The company then sold its interests to Carney Products Ltd., which peeled, sorted and stored poles at the facility.

The cleanup plan calls for removal and treatment of more than 70,000 cubic yards of soil and river sediment.

Recent Business stories

British prosecutors say 4 UK lawmakers could face charges in scandal over lavish expenses - November 10, 2009
British prosecutors say 4 UK lawmakers could face charges in scandal over lavish expenses - Four British lawmakers could face criminal charges over the expenses they claimed from taxpayers, prosecutors said Monday, marking the latest twist in a scandal over lavish spending by elected officials. More

Comment on this story   |   Be the first to comment   |  Hide reader comments

Subscribe

Blog: Patent Pending

Lights out at U energy conference. Irony police notified.

Just as Lawrence Kazmerski, a top official at the National Renewable Energy Laboratory, was about to give the keynote address at the University of Minnesota's annual E3 conference at the RiverCentre in St. Paul, the lights went out, bathing the audience in darkness and a deep sense of irony.

Recent posts